City of Corpus Christi Solar Permit Guide
In the City of Corpus Christi you pull city permits before installing rooftop solar, then request interconnection from AEP Texas. Here’s the city side.
Last updated · how we source this
Sizing a system first? Estimate your solar savings — free, no signup required.
Permits you’ll need
A building and electrical permit. Your submittal includes an electrical design (single-line diagram), a roof installation plan, equipment nameplate data, and property-owner authorization.
How to submit
Apply through the City’s Dynamic Portal (set up an online account first); forms and checklists live on the Development Services document site.
Fees & timeline
Solar permit fees typically run about $300–$825 depending on scope (building permit + plan review + technology surcharge), with roughly a 4-week review.
Outside city limits
In unincorporated Nueces County or a neighboring city, you permit through that jurisdiction instead.
Permit in hand? The next step is requesting grid interconnection from AEP Central — see its rates, buyback, fees, and application links. Or go back to the full Texas solar guide.