Texas Solar Guide
Delivery utility (TDU)

Going Solar with Lubbock P&L

Lubbock P&L serves the city of Lubbock. If you’re installing rooftop solar here, this guide covers what you’ll pay for power, how you get credited for the energy you export, the interconnection process, and the fees to expect.

See what solar would actually save you on a Lubbock P&L bill — run a free estimate (no signup required).

Rates & getting paid for solar

Approx. energy rate (your REP)

10.5¢/kWh

Approx. solar export credit

4.0¢/kWh

Lubbock P&L is your delivery utility (TDU) — it moves power and owns the meter, but doesn’t sell you energy or buy your solar directly. You choose a retail electric provider (REP), and to get paid for exported energy you’ll want a REP that offers a solar buyback plan. Rates shown are approximate.

Rate figures are best-guess estimates from 2025 data and are not a quote.

Interconnection & permit fees

Requires an interconnection agreement plus a city electrical permit. Confirm current fees with LP&L, which recently joined the competitive ERCOT market.

Fees are approximate — verify against Lubbock P&L’s current fee schedule and your local building department.

How to connect: step by step

Pull your local permits

Get a building & electrical permit from your city or county building department (your AHJ). Requirements vary locally; homeowners can often pull their own electrical permit as an owner-builder, though some jurisdictions require a licensed electrician for the interconnection wiring.

Check with your HOA

Texas’s Solar Rights Act means an HOA can’t ban rooftop solar, but it can require written approval and basic appearance standards — submit your plans first. Property Code §202.010

Request interconnection from Lubbock P&L

File a distributed generation interconnection application with Lubbock P&L. They sign an interconnection agreement, set your bi-directional meter, and issue Permission to Operate (PTO). Because Lubbock P&L only delivers power, also line up a REP with a solar buyback plan to get paid for exported energy. Lubbock P&L interconnection page

Pass inspection, then get switched on

Your city inspects the work and Lubbock P&L commissions the meter. Once you receive Permission to Operate, you can legally turn the system on and start earning credits.

For a neutral overview of going solar in Texas, see the Public Utility Commission’s guide: Thinking About Solar Panels for Your Home? Or read the full Texas solar guide.